I-5 SB S Lucile St to Spring St Pavement Repair 

PROJECT DESCRIPTION

Advanced Government Services was subcontracted to provide full service traffic control for the I-5 SB S Lucile St to Spring St project. The scope of this project cannot be understated as it involved replacing broken concrete panels, grinding the top layer of pavement in all lanes to eliminate ruts, repaving several ramps, repairing the gate at the south end of the express lanes and creating better sidewalk connections. AGS deployed a massive crew consisting of multiple crews 1000+ barrels, up to 8 arrow boards and 6 TMA’s to handle both mainline and collector distributor lanes. The operation ran on average 6 nights a week for roughly 5 months straight before the winter 2018 shut down.

PROJECT IMAGES

CONTACT US

"*" indicates required fields